| Task | Time Required | Date | Assignment | Notes |
| Get this proposal approved | | DONE | | |
| Identify someone from WebOps? willing to participate in the project | | | Noreen | Need to touch base with Shane, Austin has agreed to advise, but wants to limit involvement |
| Set up redesign project WIKI | | DONE | Jess | Basecamp site set up at http://nform.grouphub.com/projects/467571/project/log |
| Review the current IA proposal with the board and get feedback. | ongoing | | Noreen | |
| Review the current IA proposal with key stakeholders (Eric, Melissa, Shane, Austin, Jeff Tang, Gene, etc) and get feedback | ongoing | | Noreen | |
| Track all feedback in central location. | | | Noreen | |
| Develop a complete content inventory of everything on the site. | DONE | | Noreen | |
| Develop a complete inventory of all backend technologies that will be impacted by the redesign. | one week | | Chris; Austin | may decide to move later |
| Identify the key issues that need to be worked through regarding the design proposal. Current known issues include: integration of translated content, plan to implement web 2.0 applications on an iterative basis | | | Noreen/Wolf | |
| Resolve issues. | one week per issue | | | |
| Iterate the design. | one week | | James? | |
| Review the iteration with the board. | | | Board | |
| Review the iteration with the key stakeholders. | | | | |
| Gather and colate feedback from board & stakeholders | one week | | | |
| Incorporate feedback and document the final IA | one week | | | |
| Identify any content that needs to be changed or developed for this redesign | | | | |
| Determine who will update the necessary content & make assignments. | | | | |
| Set up the new IA structure in the chosen web hosting environment. | | | xian | |
| Populate the structure with navigation, labels, dummy content. | | | | |
| Perform a usability test using the structure with navigation and labels but no content or functionality. | | | | |
| Review the usability findings and determine if there are changes to be made. | | | | |
| Make iterative changes to IA based on usability test. | | | | |
| Review/signoff on the new IA structure prior to completing implementation | | | TBD--board? | |
| Populate the new IA with actual content | | | | |
| Develop a migration plan for moving functionality to new site. | | | | |
| Move functionality to new site. | | | | |
| Test functionality on new site. | | | | |
| Develop a QA plan for testing the new site for editorial accuracy, links and technical functionality | | | Eric? (editorial) | web opbs | |
| Perform QA | | | ditto | |
| Develop a marketing plan for marketing the new site, announce that the site will be changing, beta period?) | | | TBD | |
| Soft launch the site in beta | | | | |
| Make any quick-and-dirty changes as a result of the beta | | | | |
| Develop a maintenance or hand-off plan with WebOps? | | | | |
| Launch the site | | | | |
| Celebrate | | | All | |